XTO Energy Case Study - eMaint
XTO Energy Case Study2018-06-01T15:50:00+00:00

Project Description

XTO Energy Achieves 100% Work Completion Rate with eMaint CMMS

Customer Since: 2010 | Industry: Oil & Gas

XTO Energy was the largest producer of natural gas in the United States before being acquired by Exxon Mobil Corporation in 2010. XTO Energy needed a system that would allow operators to report issues at any time during their shift, includes submitting emergency work requests in the middle of the night, since the plant runs 24 hours a day. They implemented eMaint, and have seen benefits such as an increase from 70% to 100% in work completion rates with no additional staffing, as well as the anytime/anywhere access necessary for success.

  • Achieved 100% Completion Rate With No Additional Staffing

  • Gained Visibility Into Backlog at All Times

  • Support 24 Hour Operation Via Web-Based Solution

BACKGROUND

Fort Worth, TX based XTO Energy was founded in 1985, becoming the largest producer of natural gas in the United States before being acquired by Exxon Mobil Corporation in 2010. A new organization was formed to manage the global development of unconventional gas and oil resources. Doyle Lawson, Plant Foreman at the Cornell Mahoney Gas Plant currently manages the maintenance op